Colonial Pines Sewer Project
New Colonial Pines Sewer Project 5 Phase Plan Click Here to see map
Colonial Pines Homeowner Connections made as of March 2023 Click Here to see Map
- 2017 S.U.R. Construction completed the installation of a gravity sewer line beneath the Spaulding Turnpike.
- 2018 S.U.R. Construction completed the gravity sewer line from the Spaulding turnpike down Railroad Avenue to the City's sewer interceptor.
- 2019 Underwood Engineering completed the design engineering and the bidding of the Phase II Sewer Main extension into the Colonial Pines neighborhood.
- 2019 SUR Construction was the low bidder for the Phase 2 Sewer Extension Project - Construction Start planned for April 1, 2019 - This phase was completed December 2020.
- 2022 SUR Construction was the low bidder for Phase 3 Sewer Extension Project. Work has begun and is anticipated to be complete in 2023.
Any questions or concerns should be directed to Timothy Goldthwaite, PE, Assistant City Engineer at 603-332-4096.
- Phase 2 Completed
- Phase 3 In progress
- Phase 4 in Design Process
Weekly Updates:
11/14/2022
11/21/2022
11/30/2022 through winter shutdown